Update on the US 25 bridge repairs

The South Carolina Department of Transportation (SCDOT) has the following update on the US 25 bridge repairs over River Road (S-23-119) in Greenville County requiring lane closures.

This area is located at mile points 48.6 to 48.7.

  • Work on the northbound lanes beginning May 15 is on schedule to be completed during the evening of Friday, May 19.
  • Work on the southbound lanes will begin on the morning of May 29 and is scheduled to be completed during the evening of Friday, June 2, weather permitting. (The original work schedule for southbound lanes (May 22-26) has been pushed back one week due to forecasted rain.)

The repairs consist of removing damaged areas of the concrete deck, cleaning them, adding a bonding agent and replacing them with new concrete.

####